Mayor Bowser is committed to eliminating all roadways, alleys, and sidewalks in poor condition in Washington, DC by 2024 through the PaveDC initiative. This Weekly Construction Update lists all of the road, alley, and sidewalk paving projects that will be under construction during the next two weeks.
The 2021 Paving Plan is published on the PaveDC website with the start of the construction season occurring. The website also includes separate tabs for sidewalks scheduled for repair, and the Alley Restoration Plan for Fiscal Year 2021. For more information about these projects, please visit DDOT's interactive tool, PaveDC.
For frequently asked questions about the 2021 paving plan, please visit https://ddot.dc.gov
Please note: Work may be adjusted depending on weather and other conditions. Additional projects may be added to this list. DDOT contacts residents and businesses within the work zones before work begins. Unless otherwise noted, work is not conducted on weekends.
Citywide Pavement Restoration Projects
Ward 3
- Western Avenue NW between River Road NW and 47th Street NW
Ward 6
- 6th Street SE between E Street (S) SE and G Street SE
- G Street SE between 6th Street SE and 7th Street SE
- M Street NW between 4th Street NW and 5th Street NW
- N Street NW between 4th Street NW and 5th Street NW
Ward 7
- 47th Street SE between A Street SE and 49th Street SE, Astor Place SE
- 49th Place NE between Central Avenue NE and Ames Street NE
- 50th Street NE between Ames Street NE and Blaine Street NE
- 50th Street NE between East Capitol Street BN and Ames Street NE
- 52nd Street NE between Hayes Street NE and JAY Street NE
- 54th Street NE between Blaine Street NE and Clay Street NE
- 7th Street SW between G Street SW and H Street SW
- Alabama Avenue SE between 30th Street SE and 31ST Street SE
- Anacostia Avenue NE between 42nd Street NE and Nash Street NE
- Astor Place SE between 47th Street SE, 49th Street SE and 50th Street SE
- B Street SE between Bass Place (E) SE and Southern Avenue SE
- Branch Avenue SE between Lyndale Place SE and M Place SE
- Branch Avenue SE between N Street SE and POPE Street SE
- Brooks Street NE between 49th Street NE and Sycamore Road NE
- Hayes Street NE between 52nd Street NE and Division Avenue (S) NE
- Kenilworth Ter Ne between Foote Street NE and Franklin D Roosevelt Place NE
- Massachusetts Avenue SE between 34th Street SE and 34th Place SE
- Massachusetts Avenue SE between Anacostia Road SE and 34th Street SE
- Massachusetts Avenue SE between N Street SE and O Street SE
- Ord Street NE between Anacostia Avenue NE and 44th Street NE
- Ramp-36002912 between Kenilworth Avenue NE and Benning Road NE
- Ramp-36005372 between Kenilworth NE and Kenilworth Avenue NE
- Sycamore Road NE between Ames Street NE and Blaine Street NE
Citywide Sidewalk Restoration Projects
As part of DDOT's commitment to the improvement and restoration of local sidewalks, construction activities will occur at the following locations throughout the next two weeks.
Ward 1
- Belmont Road NW between 19th Street NW and 20th Street NW
- Belmont Road NW between 20th Street NW and Waterside Drive NW
- Keefer Place NW between 6th Street NW and Georgia Avenue NW
Ward 2
- 25th Street NW between I Street NW and K Street NW
Ward 3
- Rittenhouse Street NW between Broad Branch Road NW and Nevada Avenue NW
Ward 4
- 17th Street NW between Upshur Street NW and Varnum Street NW
- Kansas Avenue NW between Shepherd Street NW and Taylor Street NW
- New Hampshire Avenue NW between Shepherd Street NW and Taylor Street NW
Ward 5
- Crittenden Street NE between 16th Street NE and Queens Chapel Terrace NE
- Downing Street NE between 14th Street NE and 15th Street NE
- Queen Street NE between Montello Avenue NE and Holbrook Terrace NE
Ward 6
- Ames Place SE between 14th Street SE and 15th Street SE
Citywide Alley Restoration Projects
DDOT is improving alleys across the city. Once work begins, access to parts of the alley under construction will be closed, and parking is restricted. In emergency situations, access may be permitted by notifying DDOT. Work is estimated to take about two weeks, weather permitting.
Ward 3
- Square No1679: Alley bounded by Albemarle Street NW, Alton Place NW, and 43rd Street NW
- Square No 1300A: Alley bounded by Tunlaw Road NW, Calvert Street NW, and 37th Street NW
- Square No 1445: Alley bound by Macomb Street NW, Macarthur Blvd NW, Cathedral Avenue NW, and Sherier Place NW
- Square No 1588: Alley bound by Butterworth Place NW, 45th Street NW, Brandywine Street NW, and 44th Street NW
- Square No 1989: Alley bound by Nebraska Avenue NW, Connecticut Avenue NW, Chevy Chase Pkwy NW, and Ingomar NW
- Square No 2014: Alley bounded by Morrison Street NW, Broad Branch Road NW, McKinley Street NW, and 33rd Street NW
- Square No 2101: Alley bound by Klingle Road NW, 32nd Street NW, Cathedral Avenue NW, Cleveland Avenue NW, and 34th Street NW
Ward 4
- Square No 2243: Alley bounded by Upton Street NW, Connecticut Avenue NW, and Van Ness Street NW
Ward 6
- Square No 1065: Alley bound by Ives Place SE, 15th Street SE, K Street SE, and 14th Street SE
- Square No 763: Alley bounded by D Street SE, 2nd Street SE, C Street SE, and 3rd Street SE
- Square No 924 : Alley bound by 8th Street SE, C Street SE, 9th Street SE, and D Street SE
Citywide Guardrails and Impact Attenuators Upgrade and Repair
DDOT preventive maintenance and repair of guardrails and impact attenuators occur at the following locations throughout the next two weeks.
Ward 5
- Hawaii Avenue NB at North of Allison Street NE
- North Capitol Street SB at South of P Street
Ward 6
- 14th Street NB at ramp and EB Maine Avenue SW
Ward 7
- Benning Road WB at West of Minnesota Avenue NE
Ward 8
- I 295 NB at Exit 1A ramp to EB Pennsylvania Avenue SE
- I-295 SB at Exit 2B ramp to South Capitol Street - LEFT SW
- I-295 SB at Weigh Station SW
- Morris Road EB at West of 16th Street SE
Citywide Highway Structures Repair Projects
As part of DDOT's commitment to the improvement and restoration of Highway Structures, preventive maintenance for bridges and other highway related structures will occur at the following locations throughout the next two weeks.
Ward 3
- Chain Bridge over Potomac River
- Theodore Roosevelt Bridge over Potomac River
Ward 4
- 14th Street Bridge (Southbound) over Potomac River and Ohio Drive
Ward 6
- L'Enfant Plaza Bridge over SE Freeway
- Southwest Freeway over South Capitol Street
Ward 7
- Ramp and Beginning Road over Kenilworth Avenue Southbound
Ward 8
- Minnesota Avenue over East Capitol Street
Contact Information
For more information about the latest DDOT happenings, follow us on Twitter and Instagram; like us on Facebook; or visit the website at www.ddot.dc.gov