The Town is continuing with the implementation of the Inflow and Infiltration Phase 1 Report. The Town’s contractor, Insituform Technologies, Inc., will be cleaning and performing CCTV of the sanitary gravity sewer mains throughout the Town. This work will be completed using a no-dig, trenchless technology. The length of time the contractor will be working on any one street will vary depending on the length of pipe to be cleaned. The contractor will be working on the streets indicated below between January 9th and January 13th. To minimize road closures, please refrain from parking on the following streets per designated dates below:

Atlantic Avenue 200 Block:       Monday January 9th

Root Trail:                                Tuesday January 10th

Grace Trail:                              Wednesday January 11th

Sunrise Ave 100 Block:            Wednesday January 11th

Pine Walk:                               Thursday January 12th

Sunset Ave 300 Block:             Friday January 13th